B.TECH - Semester 8 industrial engineering Question Paper 2013 (apr)
Practice authentic previous year university questions for better exam preparation.
Sample Questions
- Why is rest allowance needed?
- What is the scope of industrial relations?
- List down some of the main causes for poor industrial relations?
- List out four reasons for keeping inventory.
- Write short note on quality circle.
- Discuss on the major reasons for low productivity? Describe some of the methods for improving productivity.
- What are the functions of industrial engineering?
- What is prototyping? List two prototyping techniques.
- Write short note on ergonomics.
- List out some of the major material handling equipments
- Write short note on group technology.
- Explain the design process. Use suitable example present the primary and secondary functions in a design.
- Write down the basic procedure of undertaking method study. Explain with suitable example an operation process chart.
- (a) What is standard time and how it is determined?
- (b) The average observed time for a repetitive work cycle in a direct time study was 3.27 mm . The worker's performance was rated by the analyst at $90 \%$. The company uses an allowance factor of $13 \%$. Calculate the standard time for this task?
- (a) Explain the differences between the concepts of industrial relations and human resources management.
- (b) Describe the methods to improve good industrial relations? OR
- (a) Explain the different type of industrial disputes in detail.
- (b) Describe the methods to impreve good industrial relations.
- (a) Write a short note on different types of inventory classification system. 20
- (b) Market demand for springs is $8,00,000$ per annum. A company purchases these springs in lots and sells them. The cost of making a purchase order is Rs. 1,200 . The cost of storage of springs is Rs. 120 per stored piece per annum. Calculate the ec...
- (a) What is the difference between quality control and quality assurance?
- (b) What is acceptance sampling? Explin with the help of suitable plots.